CONSTRUCTION BRIEF AS AT DECEMBER 2015

---

Planned Completion: December 2017

Contractual Delivery of Vacant Possession: From April 2018

Target Work Progress: 18.27%

Actual Work Progress: 18.32%

PR1_Arcadia Square.jpg